Cutting and lowering Heavy Steel Beam

Location: Mostord, Cairo, Egypt

2023

Year of completion

The beam was 10 meters height off the ground and above a sensitive production line, we had to cut it off and pull it down safely

Beam Length

9.0 m

Beam Weight

1 Ton

Project Owner

Production Factory, Egypt

Added Value to the Customer :

· Production line safety was the priority. For this reason, we strictly follow high safety norms and standards during all working processes.

· We have provided a detailed work methodology that includes all stages and details of the work.

Engineering Concept :

The beam was located above a working production line of valuable and expensive export products with total height 10 meters from the ground. We needed to cut it into small pieces so that we could pull these pieces down one by one without causing any failure in the working process of the production line.

Fast Track Solution :

· We used the Tube and Fitting System as a shoring and supporting system for the beams. Also, we used it as a platform for the labors.

· Before starting the cutting stage using the Plasma Cutting Machine, we had to cover the production line with special panels and covers with fire-resistant ability.

· After cutting each part we pull it down using the Blanco.

· We repeated the process until we pull the entire beam down.

Systems in use :

· Tube and Fitting System.

· Plasma Cutting Machine.

· Blanco and hand pallet.

IMG_5516
95cd95d0-ac56-46d1-8e9e-958aa2873603
IMG_0388
IMG_0371 2
IMG_7020
IMG_7042
IMG_7031
IMG_7058
previous arrowprevious arrow
next arrownext arrow
Shadow
Scroll to Top